Installation example
The information in this page are only a partial and summary statement of the real project.
The purpose of this text is only to provide a rough track.


Reference project:  C 1816 date 27-12-2005

Air conditioning:

Vertical AHU for the new line MAN ROLAND.
Hydraulic connection to service our equipment.
Electrical connections to service our equipment.

Brief description of the components

No. 7 Vertical AHU
No. 2 air extractors

 

For a new line MAN ROLAND 

 

 

 

 

 

 

 

 

SUPPLY LIST:

The photos and diagrams of equipment are indicative.

 

Exhaust fans - the EC -
  • Structure in aluminum profiles.
  • Panels made of galvanized and prepainted steel on the outside.
  • Inspection door.
  • Centrifugal fan comprising:
  • · Electric motor,
  • · Transmission belts,
  • · Sled tend belt
  • · Body and impeller made of galvanized steel
  • · Base of support.
  • Air flow: 25,000 m3 / h

 

AIR FILTER FOR A CAMERA POCKET
  • Galvanized steel frame.
  • Glass fiber filter media.
  • Class F5

 

SHUTTERS PAE-RIC
  • Galvanized steel case.
  • Extruded aluminum fins.
  • Compasses Ø35 for rotation of the fins.

 

BATTERY COOLING WATER
  • Galvanized frame.
  • Pipes copper / iron.
  • Fin / iron.
  • Air flow 8500 m3 / h
  • Salto heat 34-26 ° C

 

CASSONCINO DELIVERY AIR-CE -
  • version vertical column placement Floor
  • Structure in aluminum profiles.
  • Panels made of galvanized and prepainted steel on the outside, insulated with polyurethane foam injected between the two sheets.
  • Inspection door.
  • Centrifugal fan comprising:
  • · Electric motor,
  • · Transmission belts,
  • · Sled tend belt
  • · Body and impeller made of galvanized steel
  • · Base of support.
  • Air flow: 8500 m3 / h

 

SPEAKER perforated sheet self-balancing LOW SPEED '
  • Version upright at floor
  • Galvanized steel construction
  • Rear-end collision (towards wall support)
  • Internal calibration for balancing air flow in galvanized steel.

 

DUCTS AND CHIMNEYS

 
OVER OUTSIDE AIR DUCTS
  • Made of galvanized sheet.
  • Network anti-bird.
  • Grid rain DR4.
  • No. 1 from 42,500 m3 / h (5-CTA)
  • No. 2 of 8500 m3 / h (for other CTA)

 

CONDUCTED IN CONNECTION WITH CONDITIONERS
  • Made of galvanized sheet.
  • Thermal insulation except the outside the building.
  • from 42,500 m3 / h (5-CTA)

 

FIRE AIR EXPULSION
  • Constructed in galvanized
  • Version rectangular shape.
  • 25,000 m3 / h

 

INSTRUMENTATION

 
ELECTRIC VALVE
  • Electric three-way valve for regulating refrigerant

 

Electric Actuators
  • Electric actuator for adjusting damper

 

ELECTRICAL
  • Built according to CEI 17-13/1 EN60439-1.
  • Possibility of ignition of components in automatic watch program or by manual control.

 

INSTRUMENTATION
  • Electronic regulator Multiprocess to PLC.
  • Control panel on the front panel with keypad and alphanumeric display.
  • Outputs electronic control valves, pistons, etc..
  • Located in the electric plant.

 

REMOTE
  • Modem.
  • Electronic converter.
  • Tele-assistance service through our. After-sale.

 

ELECTRONIC PROBES IN THE FIELD
  • N ° 2 temperature probes
  • N ° 1 outdoor temperature probes

 

INVERTER
  • Inverter for adjustable dampers

 

TRANSPORTATION / INSTALLATION / TESTING

 
TRANSPORT
MOUNTING
  • Erection of the plant.

 

SCAFFOLDING
  • Supply of scaffolding needed for the assembly of our equipment, all the time necessary to complete the work.

 

LIFTING
  • Necessary means for lifting at the foot of the work of our equipment, all the time necessary to complete the work

 

Occupations
  • Staff help our editors to the assembly plant.

 

STARTING AND TESTING BY OUR TECHNICIANS   

CHILLED WATER HYDRAULICS

 
CHILLED WATER HYDRAULICS
  • Plant for chilled water distribution from the refrigerator to the air handling units
  • Circuit return
  • Cooling coil connection and mounting accessories
  • Thermal insulation for chilled water
  • (Excluded circulation pump and expansion tank)

 

ELECTRICAL SYSTEM

 
ELECTRICAL SYSTEM
  • Electrical system between our electrical panel and all components in the field.
  • Note
  • It remains, however, include the facility for connection to the electrical panel from our primary source.

 

 

 

 